As a result of restricted delivery, the number of homes required in the year to March 2020 has been reduced by one month. This has had a material impact on the results of the test for 19 local authorities. Staffordshire Moorlands is the only Midlands authority within this list. The national impact of the results has been assessed further in a separate Savills blog which can be accessed here.

In general, the Midlands has performed well in regards to delivering substantially more homes in the last 3 years than was required (requirement of circa 120,000 homes and delivered circa 160,000 homes). In the West Midlands, over 141% of homes were delivered compared to the requirement and in the East Midlands the figure was over 129%. However, out of the 52 local authorities in England which have failed to deliver over 75% of their housing requirement between 2017/18 - 2019/20, 5 of them are within the Midlands. These authorities will now face a presumption in favour of sustainable development (Paragraph 11d of the National Planning Policy Framework).

The table below sets out the 10 Midlands Local Planning Authorities that have failed to deliver enough housing and must now either prepare an Action Plan (delivery is below 95%), apply a 20% buffer to their Five Year Housing Land Supply calculation (delivery is below 85%) or there is a presumption in favour of sustainable development (delivery is below 75%).

Midlands Local Planning Authority

Total no. of Homes Required

Total no. of Homes Delivered

HDT: 2020 Measurement

HDT: 2020 Consequence

Ashfield

1,407

918

65%

Presumption

Bromsgrove

1,493

1,025

69%

Presumption

Broxtowe

1,024

847

83%

Buffer

Erewash

1,092

752

69%

Presumption

Gedling

1,251

855

68%

Presumption

Hinckley and Bosworth

1,277

1,172

92%

Action Plan

Newcastle-Under-Lyme

978

790

81%

Buffer

Sandwell

4,123

2,007

49%

Presumption

Walsall

2,532

2,230

88%

Action Plan

Wyre Forest

674

567

84%

Buffer

Source - MHCLG

Although the Housing Delivery Test Results above should provide applicants with a planning case for the 5 authorities that have failed to deliver 75% of their housing requirement, for the most part, this will probably not assist them significantly. All of the Midlands Local Planning Authorities listed in the table above, with the exception of Hinckley and Bosworth, are all constrained by Green Belt. In some cases, the whole authority is constrained by Green Belt outside of the urban area (Bromsgrove, Broxtowe, Gedling, Erewash, Walsall and Sandwell). For applicants, Green Belt sites bring with them a whole range of planning policy and political challenges that need to be addressed and the risks / costs associated with submitting a planning application for a Green Belt site still remain even with the presumption in favour of sustainable development.

The most risk averse option to develop a Green Belt site is to promote it through the Local Plan process for release from the Green Belt and allocation for development. Out of the 10 Midlands authorities, all but Wyre Forest are at the early stages of their Local Plan process so they are not expected to be adopted any time soon. Therefore it will be interesting to see if these authorities improve their housing delivery position in the coming years or whether they will continue to fail to deliver their housing requirement.

Attachments

  • Original document
  • Permalink

Disclaimer

Savills plc published this content on 29 January 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 29 January 2021 11:31:02 UTC.