Envoy Textiles Limited to establish a Spinning Project expansion unit at its existing factory premises in Jamirdia, Bhaluka, Mymensingh, with a production capacity of 3,710 MT cotton-polyester-spandex core-spun yarn per year. The company has also informed that the project came into operation a bit late due to the delay in shipment of machinery by the supplier caused by the Russia-Ukraine war. The company has informed that commercial production of Spinning Project expansion unit of the company commenced on 1st of April 2023, with an increased capacity of 4,200 MT yarn production per year.

Refer to their earlier news disseminated by DSE on July 15, 2021 regarding setting up Spinning Project expansion Unit, the Board of Directors of the company had planned.