DECEMBER 2016 QUARTERLY ACTIVITIES REPORT
  • Quarterly gold sales of 30,011 ounces at an average sale price of A$1,612/oz
  • Mine production increased by 12% to 36,013 ounces
  • Ramp up of ore production from the new Majestic Open Pit with 7,267 ounces mined in December and all site infrastructure now complete
  • Maxwells underground ore production commenced in October with multiple ore production blocks now established
  • Cash and bullion of A$44.1m at the end of quarter following $11.6m of capital expenditure on new mines at Maxwells and Imperial/Majestic
  • AISC of A$1,386/oz reflecting significant investment in new mines and the planned increase of higher grade stockpiles during the quarter
  • Promising results from Exploration and Resource definition drilling:
    • A new high-grade lode (Lode 56) discovered at the Daisy Complex during the quarter was promptly brought into production
    • Results from Phase 1 exploration drilling at Santa support the potential for a new, lower cost underground mine
  • Gold sales guidance of 135,000 to 145,000 ounces for FY17 unchanged

Commenting on the quarter, Silver Lake Managing Director Luke Tonkin said:

"Mount Monger continued to perform as planned with the development of the new Maxwells underground mine and Imperial/Majestic open pit mines ramping up gold production.

The FY17 Mount Monger exploration strategy of delivering lower cost discoveries proximal to existing mines and mine infrastructure had more success during the quarter with the discovery of a new high-grade lode at the Daisy Complex, Lode 56. Lode 56 has been efficiently accessed from existing mine development and gold production has commenced from development strike driving.

I would like to acknowledge the Silver Lake team for their efforts in establishing a solid foundation for a strong second half of the year."

Silver Lake Resources Ltd (ASX: SLR) Page 1 of 33

Mining (Tables 1,2,5)

Table 1: Underground Production Table 2: Open Pit Production

Underground

Ore mined from Mount Monger's underground mines totalled 98,458 tonnes at a grade of 6.5 g/t Au for 20,499 contained ounces. The 11% increase in gold production on the previous quarter was due to the additional contribution from ongoing development of the Maxwells and Cock-eyed Bob mines.

The Daisy Complex underground mine continued its consistent operating performance, contributing 71,727 tonnes at a grade of 7.5 g/t Au for 17,232 contained ounces. The Daisy Complex is expected to maintain its production performance in the second half of FY17.

A new high-grade gold lode, Lode 56, was discovered at Daisy Complex during the quarter and is accessible from existing mine development utilising existing mine infrastructure. Production from Lode 56 has commenced from strike drive development and will compliment production from existing Daisy Complex ore sources in the second half of FY17.

Consistent with the Company's operating strategy of enhancing operating margins by delivering lower cost discoveries, Lode 56 will replace some higher cost ore sources in H2 FY17 to increase cash flow generation.

Ore production at Maxwells underground (Figure 1) commenced in October, contributing 12,024 tonnes at a grade of 3.3 g/t Au for 1,271 contained ounces. Production for the quarter was sourced from ore development headings with long hole stoping activities scheduled to commence in Q3 FY17. Year-to-date development of 1,800 metres has exceeded plan and has provided multiple ore development horizons and stoping blocks for H2 FY17 and beyond.

Figure 1: Maxwells Underground Mine showing development to date and planned areas of development and stoping

Silver Lake Resources Ltd (ASX: SLR) Page 2 of 33

At Cock-eyed Bob decline development from the 345 level to the 330 level was completed during the quarter, resulting in production of 14,707 tonnes at a grade of 4.2 g/t Au for 1,996 contained ounces. Economic evaluation of the recent phase two diamond drilling results has been completed, justifying a third phase of exploration drilling which will be completed in H2 FY17. The drilling programs aim to define mining blocks 155 metres below the 330 metre level to generate a long-term mining plan.

Underground production in the second half of FY17 will focus on Daisy Complex and Maxwells while the third phase of drilling is completed and evaluated at Cock-eyed Bob.

Open Pit

Mine production from the open pits for the quarter totalled 222,250 tonnes at 2.2 g/t Au for 15,514 contained ounces, a 14% increase on the previous quarter. The increase in ore tonnes mined was due to the ramp up of production from the Majestic open pit where a total of 712,000 BCM of material was mined from the pit during the quarter.

Mining at Majestic is forecast to reach maximum production rates in Q3 with costs decreasing as the strip ratio falls.

Mining from the Imperial open pit (adjacent to the Majestic open pit) is forecast to commence in Q3 FY17.

Processing (Tables 3,4,6)

Table 3: Production Processing Table 4: Gold Sales and Revenue

Mill feed during the quarter was sourced from the Daisy Complex, Maxwells and Cock-eyed Bob underground mines, the Majestic open pit and Santa stockpiles. Ore milled for the quarter totalled 324,592 tonnes at a blended grade of 3.2 g/t Au for 30,662 recovered ounces. Recovery fell marginally as expected with the introduction of Majestic ore to the mill feed blend.

Gold sales for the quarter totalled 30,011 ounces compared with 34,405 ounces sold in the previous quarter. December quarter sales were lower than the previous quarter due to high-grade Majestic ore deliveries only landing on the Randalls mill feed stockpile late in the quarter and not being fed to the processing plant by quarter end. As a result, 31 December stockpiles increased to approximately 362,000 tonnes (containing 17,300 ounces), a 22% increase on the 30 September 2016 inventory balance.

Milling rates at the Randalls Gold Processing Facility are expected to be marginally lower in H2 FY17 however mill feed head grade is expected to increase with 35% of mill feed tonnes and 53% of mill feed ounces sourced from underground operations. The remaining feed will be comprised of open pit ore and available ore stockpiles.

The Company's gold sales guidance for FY17 remains unchanged at 135,000 to 145,000 ounces.

Mount Monger Operation - Mining

Units

Mar Qtr 2016

Jun Qtr 2016

Sep Qtr 2016

Dec Qtr 2016

YTD FY17

FY16

Underground - Daisy Complex

Ore mined

Tonnes

82,590

70,369

74,747

71,727

146,474 318,

717

Mined grade

g/t Au

6.5

7.6

7.2

7.5

7.3

7.0

Contained gold in ore

Oz

17,351

17,185

17,366

17,232

34,598 72,

208

Underground - Cock-eyed Bob

Ore mined

Tonnes

32,141

14,833

8,970

14,707

23,677 100,

748

Mined grade

g/t Au

4.9

3.7

3.9

4.2

4.1

4.2

Contained gold in ore

Oz

5,079

1,769

1,118

1,996

3,114 13,

533

Underground - Maxwells

Ore mined

Tonnes

-

-

-

12,024

12,024

-

Mined grade

g/t Au

-

-

-

3.3

3.3

-

Contained gold in ore

Oz

-

-

-

1,271

1,271

-

Open Pit - Lucky Bay

Ore mined

Tonnes

27,606

-

-

-

- 100,

022

Mined grade

g/t Au

3.5

-

-

-

-

4.2

Contained gold in ore

Oz

3,138

-

-

-

- 13,

512

Open Pit - Santa Area

Ore mined

Tonnes

237,960

311,822

125,476

-

125,476 757,

126

Mined grade

g/t Au

1.5

1.7

2.4

-

2.4

1.7

Contained gold in ore

Oz

11,794

17,391

9,504

-

9,504 41,

395

Open Pit - Majestic

Ore mined

Tonnes

-

-

68,055

222,250

290,305

Mined grade

g/t Au

-

-

1.9

2.2

2.1

Contained gold in ore

Oz

-

-

4,098

15,514

19,612

Open Pit - Maxwells

Ore mined

Tonnes

-

9,583

-

-

- 9,

583

Mined grade

g/t Au

-

1.7

-

-

-

1.7

Contained gold in ore

Oz

-

517

-

-

-

517

Total ore mined

Tonnes

380,297

406,607

277,248

320,708

597,956 1,286,

196

Mined Grade

g/t Au

3.1

2.8

3.6

3.5

3.5

3.4

Total contained gold in ore

Table 5: Mount Monger Operation - mine produc

Oz

tion statistics

37,362

36,862

32,086

36,013

68,099 141,

165

Silver Lake Resources Limited published this content on 24 January 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 24 January 2017 03:30:01 UTC.