Rizal Resources Corporation announced production and earnings results for the month ended October 2017. Gold production for October totalled 765oz, Bullion sold totalled 361oz. Mill availability was 98%, less than planned mill feed resulted in utilisation of only 62%. Mill throughput was 3760 tonnes, a marginal increase over September's 3,561 tonnes. Total silver produced was 411 oz.

For the month, the company announced total revenue of CAD 559,050. Operating loss was CAD 35,941. Total capex for October was CAD 438,000 (PHP 18.2 million) of which Mine capex was 97%.