Emerald Resources NL provided an update on a number of aspects as Emerald continues on the path to develop the Okvau Gold Project. Grid Power: The power line to supply grid power to the Okvau Gold Project is well advanced with the execution of an MoU imminent to confirm power availability from December 2019. Works completed and in progress to date include: Route survey completed; Power line corridor clearing completed to site; Concrete foundations - 54% complete; Transmission towers erected - 36% complete; and Stringing of power lines - 12% complete. The power line contractor continues to advise works are scheduled for completion prior to end of 2019. The provision of grid power is a critical step to production and it is an extremely positive outcome that grid power availability is expected upon commissioning of the operations. Access Road: Negotiations for the construction of the access road are nearing completion which include the construction of a 35 tonne bridge across the Prek Te River. Independent to Emerald, a third party has commenced work to improve road access. Further, as part of the road access negotiations, Emerald will have the use of a temporary 20 tonne bridge to cross the Prek Te River to allow continuous access to the Okvau site throughout the May - September wet season.