Donaco International Limited announced that the soft opening of its new five star resort hotel and casino in Lao Cai, Vietnam, will be delayed from early March to early May 2014. This two month delay in the soft opening is due to an administrative delay in the re-registration of the company's investment certificate. As stated in the company's announcement to the market on November 14, 2013, the process for re-registering the investment certificate is led by the Lao Cai Provincial Government, and is not directly controlled by the company.

There is no delay in the construction schedule for the new hotel and casino. As a result, at the date of the soft opening in early May, there will be a substantially larger number of hotel rooms completed in the new property.