Deep Well Oil & Gas, Inc. providing an update for the Steam Assisted Gravity Drainage oil sands project at Sawn Lake, Alberta, Canada. Production in 2016 at the Sawn Lake Demonstration Project has reached a steady state production level over the past six weeks of 600 barrels per day (BOPD) (150 BOPD net to DWOG) with an instantaneous steam-oil ratio (ISOR) of 2.2 from the one SAGD well pair. Production, on a 100% basis, averaged 596 BOPD with an ISOR of 2.2 in January and has averaged 620 BOPD with an ISOR of 2.1 during the first 21 days of February.