ASX ANNOUNCEMENT | 11 March 2022 |
Ardmore Phosphate Rock Project Update
Highlights
- Construction commenced on outstanding Non-Process Infrastructure for the Initial Production Plant.
- First production of high-grade beneficiated product on schedule for July 2022.
- Continued high phosphate rock prices.
Centrex Limited (ASX:CXM) ("Centrex" or the "Company") is pleased to provide an update on recent developments at the Company's flagship Ardmore Phosphate Rock Project.
ARDMORE PHOSPHATE ROCK PROJECT, QLD
Direct Application Rock Phosphate (DAPR)
Marketing efforts continue to promote DAPR sales. Sales continue to grow albeit from a small base. Pleasingly, we are now receiving repeat customer business.
Initial Production Plant
Centrex personnel mobilised to site late February 2022. Site construction commenced as scheduled early March 2022 and is expected to be completed by July 2022. To date, more than 18 truckloads of materials have been delivered to site and installed (Figures 1,2,3 and 4). The bulk of the remaining work is the completion of non-process infrastructure (power distribution and water supply).
Plant commissioning and first product is expected to take place in July 2022 with first shipment in August 2022.
The Company recently received minor amendment approval to its existing Environmental Approval. This allows the Company to recommence mining and undertake processing operations onsite. A preferred mining contractor has been selected and is expected to mobilise to site in April 2022.
1 | P a g e
Centrex Limited ACN 096 298 752 - 44 Waymouth St. 6FL, Adelaide, SA, 5000 - www.centrexlimited.com.au
For personal use only
Planning and contract discussions are well advanced for production and shipment of five individual 5,000 tonne trial parcels (25,000t total) to be sent to customers for their prequalification. Negotiations continue with these customers for potential longer term arrangements over the remaining 50% of uncommitted first right production offtake.
The Company is investigating the potential to operate the trial plant beyond the production of the initial trial shipments. This has the potential to provide early cashflow and further de-risk the project through greater customer acceptance.
Commercial Plant
Front Engineering and Design continues for the 800,00 tpa commercial plant.
GRES have been employed to complete the stage 1 scope of work (SOW), focusing on optimising the physical location of the process plant and is expected to take four months to complete.
Three potential plant locations are being examined in detail. These are the Ardmore site, a potential site near Mt Isa and Townsville. Initial results favour building the commercial plant at a site other than Ardmore.
PHOSPHATE ROCK PRICE / MARKET
The Company is closely monitoring recent positive developments in phosphate rock prices and restricted supply, which continue to support the development of the Ardmore Phosphate Rock Project.
High phosphate rock prices continue to be supported by strong demand and the restricted supply of Chinese fertilisers. The FOB North Africa (68-72% BPL) benchmark price for February 2022 was US$172.5 per tonne (World Bank Commodities Price Data, 2 March 2022).
Phosphate rock supply is also being impacted by growing limits and bans on Russian phosphate rock. The Australian Government recently recognised agriculture chemicals current and future supply chain vulnerabilities through the Office of Supply Chain Resilience listing it as one of the categories considered important to Australia's national interest (https://www.pm.gov.au/media/virtual-address-afr-business-summit).
CRU, one of the worlds leading analysts on Rock Phosphate, reports that OCP Morocco (the worlds leading Phosphate Rock producer) are "now agreeing some 68-72% BPL phosphate rock contracts for the first quarter 2022 at $245-300/t FOB", reflecting a $90/t rise on the 2021 Q4 Morocco (68-72% BPL) price assessment at $140-225/t FOB. (Feb 24 2022).
The Company's updated Definity Feasibility Study (DFS) in August 2021 used a benchmark phosphate price of US$125 per tonne. The current US$172.5 per tonne benchmark phosphate price represents a 38 % increase compared to US$125 benchmark price used in the August 2021 DFS.
For personal use only
FUTURE MILESTONES
- Completion of the Initial Production Plant.
- Commissioning and first production from the Initial Production Plant.
- First shipment and sale.
- Finalise further offtake Agreements
Figure 1. Storage Container being lifted into position, Ardmore Phosphate Rock Project March 2022.
For personal use only
Figure 2. New fuel storage facility, Ardmore Phosphate Rock Project March 2022.
Figure 3. Initial Production Plant, Ardmore Phosphate Rock Project March 2022.
For personal use only
Figure 4. New office and crib rooms. Ardmore Phosphate Rock Project March 2022
This ASX announcement has been approved and authorised for release by the Board of the Company.
For further information please contact:
Robert Mencel | Jonathan Lindh |
Managing Director | Company Secretary |
Centrex Limited | Centrex Limited |
Ph (08) 8213 3100 | Ph (08) 8213 3100 |
For media enquiries, please contact: | |
Grant Law | |
Grant Law Public Relations | |
Ph (61) 488 518 414 | |
Email - grant@grantlaw.com.au |
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Centrex Ltd. published this content on 11 March 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 11 March 2022 02:45:05 UTC.