PROGRESS REPORT FOR THE PERIOD MAY 02, 2024
CONTENTS
INTRODUCTION | 3 | |
SUMMARY OF IPO FUNDS GENERATED | 3 | |
IMPLEMENTATION STATUS | 4 | |
1. | UTILIZATION OF IPO PROCEEDS ON LOCAL COST COMPONENTS | 4 |
2. | SHIPMENT AND INSTALLATION OF MI DA ROLLING MILL | 4 |
3. | SHIPMENT AND INSTALLATION OF AIR SUPRESSION UNIT | 5 |
4. | PRE COMMISSIONING AND COMMISSIONING | 5 |
ANNEXURE - I | 6 | |
ANNEXURE - II | 8 |
2 | P a g e
PROGRESS REPORT
INTRODUCTION
This Progress report is being submitted as per Regulation 16 of the Public Offering Regulations, 2017 & in compliance with the requirement specified in clause 4.1.10 of the prospectus to the issue of the Company.
AGHA STEEL INDUSTRIES LIMITED carried out a successful IPO in October 2020 to finance its expansion at estimated cost as detailed below:
Break up of IPO Proceeds Utilization | Rupees |
Civil Works | 377,380,707 |
Electrical | 486,387,463 |
Mechanical | 458,231,960 |
Duties and Others | 534,403,866 |
Air Separation Unit | 399,735,446 |
LC Discount Charges | 193,860,558 |
Contingency | 150,000,000 |
Working Capital Requirement | 1,000,000,000 |
In this respect, We would like to update the following progress has been achieved on the implementation of the phase II during the period ended Nov 02, 2022 after listing on PSX and in accordance with financial results uploaded at PSX in respect of aforementioned projects in the ensuing pages.
SUMMARY OF IPO FUNDS GENERATED
Description | Rupees |
Issuance of 120 million ordinary shares at floor price of Rs. 30 per share | 3,600,000,000 |
Excess funds received - Share Premium at Rs. 2 per share | 240,000,000 |
Less: Share issuance costs | (225,275,000) |
Net IPO Proceeds | 3,614,725,000 |
3 | P a g e
PROGRESS REPORT
IMPLEMENTATION STATUS
1. UTILIZATION OF IPO PROCEEDS ON LOCAL COST COMPONENTS:
Break up of IPO Proceeds | Completed | Cost to be | Already | Percentage of |
Utilization | incurred | utilized | Completion | |
Civil Works | Completed | 377,380,707 | 1,073,825,000 | 100% |
Electrical | Completed | 486,387,463 | 452,023,000 | 90% |
Mechanical | Completed | 458,231,960 | 665,277,000 | 90% |
Duties and Others | Completed | 534,403,866 | 535,410,000 | 90% |
Air Separation Unit | Completed | 399,735,446 | 694,329,000 | 100% |
LC Discount Charges | Completed | 193,860,558 | 193,860,558 | 100% |
Contingency | Completed | 150,000,000 | - | N/A |
Working Capital | Completed | 1,000,000,000 | - | N/A |
Requirement | ||||
3,6000,000,000 | 3,614,725,000 |
2. SHIPMENT AND INSTALLATION OF MI DA ROLLING MILL:
S.no | Commitment made in | Start | date | Completion | Current |
prospectus | (disclosed in | date (disclosed | Status | ||
prospectus) | in prospectus) | ||||
1 | Shipment of the Mi.Da | January 2020 | March 2020 | Completed | |
rolling mill | |||||
2 | Installation of the of | September | December 2020 | In Progress | |
Mi.Da rolling mill. | |||||
2020 | |||||
Rational for Delay, If any
N/A
Macro-economic
factors
Please refer 'Annexure - I' for pictorial representation of the under process Civil, Electrical and Mechanical works involved in implementation of MI DA rolling mill would give an idea over pace of progress
4 | P a g e
PROGRESS REPORT
3. SHIPMENT AND INSTALLATION OF AIR SUPRESSION UNIT:
S.no Commitment made | Start | date | Completion | Current | Rational for Delay, If any | |
in prospectus | (disclosed in | date | Status | |||
prospectus) | (disclosed in | |||||
prospectus) | ||||||
1 | Shipment of Air | August 2020 | October 2020 | Completed | N/A | |
Separation Unit | ||||||
2 | Installation of Air | November | December | Completed | N/A | |
Separation Unit | 2020 | 2020 | ||||
Please refer 'Annexure - II' for pictorial representation of the under process Civil, Electrical and Mechanical works involved in implementation of Air Separation Unit would give an idea over pace of progress.
4. PRE-COMMISSIONING AND COMMISSIONING:
S.no Commitment made | Start | date | Completion | Current | Rational for Delay, If any |
in prospectus | (disclosed in | date | Status | ||
prospectus) | (disclosed | in | |||
prospectus) |
1 | Pre-Commissioning | January 2021 | March 2021 | In progress | Macro-economic factors / |
and Commissioning | other economic issues | ||||
___________________ | ____________________ |
Company Secretary | Chief Financial Office |
5 | P a g e
PROGRESS REPORT
ANNEXURE -A
CIVIL, ELECTRICAL AND MECHANICAL WORKS INVOLVED IN IMPLEMENTATION OF MI DA ROLLING MILL
6 | P a g e
PROGRESS REPORT
7 | P a g e
PROGRESS REPORT
ANNEXURE - II
CIVIL, ELECTRICAL AND MECHANICAL WORKS INVOLVED IN IMPLEMENTATION OF AIR
SEPARATION UNIT