ASX ANNOUNCEMENT

QUARTERLY ACTIVITIES REPORT For the quarter ended 31 March 2022

88 Energy Limited (ASX:88E, AIM:88E, OTC:EEENF) (88 Energy or the Company) provides the following report for the quarter ended 31 March 2022.

Highlights

Project Peregrine (100% WI)

  • Spud of the Merlin-2 well occurred on 7 March 2022 and successfully reached Total Depth of 7,334 feet on 22 March 2022. All three Nanushuk reservoir targets (N20, N19 and N18) were penetrated with elevated mud gas readings and oil shows noted in cuttings.

  • Wireline logging program completed with provisional analysis indicating reservoir quality at Merlin-2 was insufficient to warrant a production test and the MDT tool was unable to obtain fluid samples from target zones, despite encouraging oil shows and Logging While Drilling (LWD) data.

  • A decision to plug the well and commence demobilisation from the Merlin-2 well site was made just prior to the end of the quarter.

Project Longhorn (~73% WI)

  • Production rate exceeding 400 BOE gross per day (~70% oil) at the end of March 2022.

  • Successful completion of the first planned capital-efficient work-over in March 2022.

  • First net cash flow distribution received in March 2022 of ~A$0.6M.

Project Icewine (~75% WI)

  • Preliminary 3rd party mapping of the Shelf Margin Delta (SMD) play indicates extension of the play fairway from neighbouring Pantheon Resources acreage onto Project Icewine's acreage.

  • Mapping of Seabee Lower Basin Floor Fan (BFF) and Slope Fan System (SFS) nears completion.

  • Discussions and negotiations with potential farm-in parties into Project Icewine.

  • Completion of independent resource update scheduled for Q2 2022.

Umiat Oil Field (100% WI)

  • Ongoing optimisation studies, including evaluation of lower cost and innovative development options.

Corporate

  • Commenced trading on the US OTCQB market on 19 January 2022 under code EEENF.

  • Oversubscribed share placement on 14 February 2022, raising A$32.1M gross proceeds (A$30M net).

  • Acquired ~73% non-operating working interest in Texas oil and gas production assets for US$9.7M, consisting of US$7.2M cash and US$2.5M in 88 Energy shares.

  • Cash of A$32.6M and no debt (as at 31 March 2022).

QUARTERLY REPORT

For the period ended 31 March 2022

Project Peregrine (100% WI)

Merlin-2 Appraisal Well

The Merlin-2 well was designed to appraise the N20, N19 and N18 horizons (targeting a net mean aggregate prospective resource of 6521,2 million barrels) which were encountered in Merlin-1 and returned compelling evidence of hydrocarbons across these three separate zones. The Merlin-2 well represented a move east from Merlin-1 towards the shelf edge where thicker and higher porosity / permeability formation was anticipated with the primary target being to collect hydrocarbon samples from the target zones.

The Arctic Fox rig commenced drilling the Merlin-2 appraisal well, located on Project Peregrine in the NPR-A region of the North Slope of Alaska, on 7 March 2022. The surface hole was successfully drilled to 2,005 feet, the surface casing installed and cemented, and the Blow Out Preventer (BOP) system tested on 17 March 2022. The Arctic Fox reached Total Depth (TD) of 7,334 feet on 22 March 2022 and ceased drilling. The Arctic Fox exceeded expectations in terms of drilling performance, with the well reaching TD safely and efficiently.

All three Nanushuk targets (N20, N19 and N18) were penetrated during drilling, with Logging While Drilling (LWD) data and physical cuttings collected throughout the Merlin-2 program. Observations of LWD logs and drill cuttings collected during drilling revealed target intervals were thicker than those encountered in Merlin-1 and preliminary analysis of the LWD data indicated sufficient permeability / porosity to obtain a hydrocarbon sample which prompted running a sophisticated Wireline logging program to confirm reservoir quality and to establish if mobile hydrocarbons were present.

The Wireline logging program consisted of multiple runs that included the use of Schlumberger's MDT (Modular-Formulation Dynamics Testing) tool to conduct fluid sampling and acquire flow potential measurements, side wall cores and image logs. Unfortunately, the MDT tool was unable to obtain fluid samples from target zones due to the tightness of the formation in this location. Plugging, abandonment and demobilisation of the Merlin-2 well is underway and will be completed in April 2022.

The results of Merlin-2 are largely consistent with the Merlin-1 exploration well drilled in 2021, with strong fluorescence, oil sheen, petroliferous odour and cut noted in the drilling cuttings, elevated C2-C5 mud gas readings over the target zones with total gas significantly above background gas readings and also evidence from the reservoir sampling tool of moveable hydrocarbons. Both Merlin wells were drilled on sparse, vintage 2D seismic data, which provides a narrow field of view of the reservoir and limited optionality on driling locations. 88 Energy will now assess the merits of a future 3D seismic acquisition program allowing modern processing of data at future drilling locations in order to optimally test and determine the potential comerciality of the Project Peregrine acreage.

88 Energy will also undertake detailed analysis of all data obtained from the Merlin-2 drilling program and evaluate potential future appraisal activities within the Project Peregrine acreage, which includes additional independent drilling locations such as the Harrier-1 prospect to test the N-14 and N-15 horizons.

1. Mean unrisked prospective resource - Net Entitlement to 88 Energy

2. Cautionary Statement: The estimated quantities of petroleum that may be potentially recovered by the application of a future development project relate to undiscovered accumulations. These estimates have both an associated risk of discovery and a risk of development. Further exploration, appraisal and evaluation are required to determine the existence of a significant quantity of potentially movable hydrocarbons.

Page 2 of 7

QUARTERLY REPORT

For the period ended 31 March 2022

Project Longhorn (~73% WI)

On 21 February 2022, 88 Energy executed a binding Securities Purchase Agreement (SPA) for the acquisition of a ~73% average net working interest in established conventional oil and gas production assets in the proven Permian Basin, onshore Texas, U.S. The oil and gas assets, collectively known as Project Longhorn contain certified net 2P reserves of 2.05MMBOE1. The purchase price for the acquisition was US$9.7M, consisting of US$7.2M cash and US$2.5M in 88 Energy shares (~98.1 million shares at an issue price of A$0.035 per share).

The acquisition represents 88 Energy's first move into producing oil and gas assets and is in line with Company's strategy to build a successful oil and gas exploration and production Company.

The Project Longhorn assets are located in the attractive Permian Basin, with ~1,300 net acres and well understood geology with low technical risk. The assets consist of 9 leases with 32 producing wells and associated infrastructure. Most of the existing production wells have been in operation for several years. Lonestar I, LLC will retain a ~24% net working interest in the assets and, through an affiliate, will remain Operator, with the remaining working interests retained by existing Joint Venture partners.

As part of the acquisition, 88 Energy agreed to a low-cost work program for 2022 that includes seven work-overs, which are expected to double current production rates by the end of 2022.

In March 2022, the operator of the Longhorn production assets, Lonestar I, LLC, successfully completed the first planned capital-efficient work-over since the acquisition, on time and on budget, which has delivered an immediate increase to the total oil and gas production rates of the project.

Production from the Longhorn wells exceeded 400 BOE per day gross (approx. 70% oil) at the end of March 2022. This represents an increase of over 30% since the completion of the acquisition in mid-February 2022. The production increase provides additional direct exposure to the higher WTI oil prices and an accelerated pay-back on both the acquisition of the assets and the capital investment in the work-overs.

Project Longhorn has exceptionally low operating costs (lifting costs), which provides high margins from production. First cash receipts from Project Longhorn were received by 88 Energy in March 2022, which comprised a payment of approximately A$0.6 million (net to 88 Energy and net of OPEX/CAPEX).

Project Longhorn remains on track to complete the targeted seven capital development activities this year, which is expected to approximately double current production rates by the end of CY2022.

Table 1: Project Longhorn Reserves (barrels of oil equivalent; millions)

1.

Further ASX Listing Rule 5.31 Information (Notes to Reserves) related to these Reserves is provided in Appendix 1 of the announcement dated 21 February 2022 as released on ASX, AIM and OTCQB markets.

Reserves Cautionary Statement: Oil and gas reserves and resource estimates are expressions of judgment based on knowledge, experience, and industry practice. Estimates that were valid when originally calculated may alter significantly when new information or techniques become available. Additionally, by their very nature, reserve and resource estimates are imprecise and depend to some extent on interpretations, which may prove to be inaccurate. As further information becomes available through additional drilling and analysis, the estimates are likely to change. This may result in alterations to development and production plans which may, in turn, adversely impact the Company's operations. Reserves estimates and estimates of future net revenues are, by nature, forward looking statements and subject to the same risks as other forward-looking statements.

Page 3 of 7

QUARTERLY REPORT

For the period ended 31 March 2022

Project Icewine (~75% WI)

88 Energy is progressing activities well at Project Icewine, following the drilling results of the Talitha-A well in Q1 2021, where Pantheon Resources (Pantheon) reported oil shows in multiple formations in the Talitha-A well [refer AIM:PANR release dated 19 April 2021]. The Talitha-A well is located 2.8 miles north of the Project Icewine permit boundary. The Talitha-A well was suspended following a production test of the Kuparuk, with Pantheon announcing its intention to return to test additional targets, namely the Seabee Lower Basin Floor Fan (BFF), the Slope Fan System (SFS) and the Shelf Margin Delta (SMD), during the 2022 drilling season. Earlier this year, Pantheon re-entered the Talitha-A well and individually flow-tested the BFF target and the SFS target, which resulted in the sustained recovery of light oil over a three-day period from each test. All targets are interpreted by the Company, and independently, to extend into the Project Icewine acreage.

88 Energy's ongoing assessment of the SMD, SFS and BFF play fairways onto its Project Icewine acreage is progressing as planned. Preliminary independent third-party mapping using available well information from presentations publicly released by neighbouring acreage holder, Pantheon, plus internal 88 Energy data, including Icewine-1 and Icewine-2 well logs and existing 2D seismic, indicates that all play fairways extend into the Project Icewine lease holding. The source rocks (GRZ/HRZ) for the Brookian plays within the Project Icewine area are modelled to be within the oil mature window, with historical wells reporting abundant oil shows and interpreted oil saturations from electric log data.

Recent Pantheon wells - Alkaid-1, Talitha-A and Theta West-1 - have flowed 35 to 40⁰ API oil from multiple Brookian reservoirs. Pantheon testing has confirmed reservoir deliverability of light, sweet oil (refer AIM:PANR releases dated 7 and 21 February 2022), which 88 Energy believes is positive for the prospectivity of the adjacent Project Icewine acreage.

Following these recent results, 88 Energy has a positive view of the potential of the SMD, SFS and BFF play fairways that extend onto the Icewine acreage. In particular, the Company notes the relative consistency of results over a large area to the north are suggestive of reasonably homogeneous reservoirs that potentially extend into 88 Energy's acreage. The Company also notes Pantheon's planned development wells are expected to produce at rates of over 1,000 BOPD per well via long horizontal wells with multi-stage hydraulic fracturing technology (refer AIM:PANR release dated 24 January 2022).

88 Energy is in the process of finalising mapping of the SFS and BFF play fairways onto the Icewine acreage and expects this work to be completed in April 2022. Once complete, the combined mapping of the three prospects (SMD, SFS and BFF) is set to form the basis of an updated resource estimate at Project Icewine, scheduled for completion in Q2 2022.

During Q1 2022, 88 Energy commenced discussions in relation to a potential farm-out of the Project Icewine acreage. Due diligence activities and negotiations are advancing with a third party, including the related work program terms and structure. Execution and completion of the potential transaction is not guaranteed and remains subject to all documentation being agreed and due diligence completed. There is no guarantee that negotiations will lead to a binding agreement or a completed transaction.

Page 4 of 7

QUARTERLY REPORT

For the period ended 31 March 2022

Umiat Oil Field (100% WI)

In Q1 2021, 88 Energy acquired the Umiat Oil Field. As part of the acquisition, the Company received the Umiat data pack which includes Umiat 3D seismic data. The Umiat 3D survey abuts the southern edge of the Project Peregrine lease blocks. Integrating the Linc/Malamute seismic interpretation has provided a better understanding of the Peregrine reservoir geometries to the north as well as enriching our petrophysical database with additional well control (Umiat-8 and Umiat-23H).

Internal reinterpretation of modern 3D seismic is suggestive of untested reservoirs at Umiat. Prospects have been mapped in the footwall of the Umiat structure as well as downdip from the proven oil zone in the hanging wall. Initial internal volumetric calculations suggest there may be multi-million barrels of recoverable oil combined in the hanging wall and footwall. Both prospects are deeper than the current reserves at Umiat which should have a positive impact on productivity.

Development studies continued in the quarter, focusing on the potential integration of Ultra Low Sulphur Diesel (ULSD) production with previous studies. Initial screening economics suggest that this development option adds further value to a future Umiat development, considering the high cost of diesel (currently ~US$6-7/gal) on the North Slope of Alaska.

A separate Umiat-23H well performance review was also finalised during the quarter. This well was drilled in 2014 by a previous owner and flowed at a sustained rate of 200 BOPD with no water, and a maximum rate of 800 BOPD. The review concluded that this well significantly underperformed due to poor drilling and completion techniques. A more conventional trajectory and completion design for a 5000 ft horizontal section was modelled to produce at stabilised rates of between 800 and 1600 BOPD. Consequently, an opportunity exists for the optimisation of historic subsurface development plans.

Yukon Leases (100% WI)

The Yukon Leases contain the 82 million barrel1 Cascade Prospect, which was intersected peripherally by Yukon Gold-1 and classified as a historic oil discovery.

The Company continues to complete due diligence and commercial assessment of a joint development with near-by resource owners.

Corporate

On 19 January 2022, the Company advised that its application to join the OTCQB Market in the United States had been accepted and the Company's shares were listed for trading under the code EEENF. The OTCQB Venture Market is for entrepreneurial and development stage US and international companies and 88 Energy sought OTCQB quotation to provide North American investors with enhanced accessibility and liquidity in trading the Company's shares. The quotation delivered 88 Energy access to one of the largest investment markets in the world at relatively nominal cost (compared to traditional major exchanges) and with practically no additional compliance requirements. The OTCQB Market has robust financial reporting and corporate governance regulations which are effectively satisfied by the Company, through its ongoing compliance with ASX Listing rules and AIM rules.

On 14 February 2022, the Company advised that it had successfully completed an oversubscribed bookbuild to domestic and international institutional investors to raise A$32.1M before costs (the Placement). This was achieved through the issue of 918,650,793 fully paid ordinary shares in the Company at an issue price of A$0.035 (equivalent to £0.018) per New Ordinary Share).

1. Refer to 88 Energy release dated 7th November 2018. Note cautionary statement on page 2.

Page 5 of 7

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

88 Energy Limited published this content on 14 April 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 14 April 2022 03:04:09 UTC.