UR-Energy Inc. provided the following update on construction at its Lost Creek Project and the legal proceeding filed in November seeking review of the BLM's Record of Decision. Construction continues to advance at the Lost Creek Project, with power and roads completed to the construction site. All footings, walls and pillars are complete within the foundation of the plant building and additional work on the plant pad is continuing.

Wellfield construction is progressing as planned, with work continuing to case and complete the initial production wells. Subsurface engineering work is nearing completion on both deep disposal wells drilled to date.