OM Metals Infraprojects Ltd. announced that it has bagged hydro mechanical order worth of INR 405 million from BHEL and MB Power. The first order is from Bharat Heavy Electricals Ltd. to execute the hydro mechanical works for a 28 MW hydro-electric power project in Nyaborongo district at republic of Rwanda, Africa. The scope of the activity includes design, fabrication, manufacturing, transportation, erection, testing and commissioning of Gates and Pen Stocks.

The project is expected to be completed by December 2013. The second order from Moser Baer Power Madhya Pradesh Limited to execute the hydro-mechanical works on River Song barrage. This 2,520 MW project will be installing 7 radial gates.

The company is engaged to supply of hydro mechanical equipments including general & mandatory spares for hydro-mechanical work which is expected to complete by March 2014. This power project is situated in the district of Anuppur, Madhya Pradesh.