All dollar amounts are in Canadian dollars unless otherwise stated.
Accomplishments during 2020 include the completion of several significant milestones.
- A Preliminary Economic Assessment ("PEA") of the Phase 1 Development Plan for the
Dasa Uranium Project was filed, indicating an initial 12-year mine schedule to produce 44.1 million pounds U3O8, with an average processed grade of 5,396 ppm; - The PEA estimates cash costs of US
$16.72 /lb U3O8, including corporate and all other off-site costs, and an all-in sustaining cost of US$18.39 /lb U3O8; - Based on a Base Case U3O8 price of US
$35 /lb, the PEA estimates an after-tax NPV discounted at 8% at$211 million for an after-tax IRR of 26.6%; - The Mining Permit was granted by the Government of
Niger onDecember 23, 2020 , in response to the Company's application submitted onSeptember 25, 2020 ; - A Hydrogeological water well drilling and testing program was completed to support the Mining Permit application;
- An Environmental Impact Statement was completed and filed with the Government of
Niger ; - A preliminary geotechnical report was completed and identified the drilling required to finalize geotechnical inputs to the final mine design;
- A Pilot Plant study was completed to confirm and optimize the processing plant flow sheet, the results of which will be reported in early 2021.
Turkish Zinc Joint Venture:
- The Turkish zinc production plant ramped up successfully from the 2019 expansion and modernization and realized improved operating efficiencies;
- Zinc prices rose by the end of the year and operating rates recovered from COVID-related steel industry downturn that affected the supply of electric arc furnace dust to the plant in the first half of the year.
Corporate:
- The Company completed a private placement of 5,538,335 Units on
May 15 th at a price of$0.60 per Unit for gross proceeds of$3,323,000 . Each Unit comprised one common share and one-half warrant exercisable at$0.85 per common share for 24-months subject to an accelerator clause should the shares trade at or above a volume weighted average trading price of$1.10 for 20 consecutive days; - Global Atomic continues to receive management fees and sales commissions from the Turkish JV, helping to offset corporate overhead costs, dividend income is scheduled to resume following re-payment of project debt associated with the plant expansion and modernization;
- In
the United States , Global Atomic common shares are now DTC eligible and received Blue Sky clearence in all but five states.
As a reflection of all of these accomplishments, at the end of 2020 as compared with the closing share prices at the end of 2019, the price of Global Atomic shares increased by 231% to
Global Atomic is working towards the following significant milestones in 2021:
- Announce Pilot Plant results expected to validate the process flowsheet and confirm the metallurgy of the
Dasa ore; - Complete the Geotechnical drilling campaign to finalize inputs to the final mine design;
- Complete the Phase I Dasa Uranium Project Bankable Feasibility Study;
- Arrange project financing with the goal of funding initial mine development in early 2022 and enter into off-take agreements with Utilities for the purchase of yellowcake from the
Dasa Mine ; - Complete the payback of the project loan associated with the 2019 expansion and modernization of the zinc production plant in
Turkey , assuming current zinc prices and plant throughput.
I am proud of our team and thank them for their diligence and hard work. I particularly thank our local teams at the
We wish you a Happy, Healthy and Safe 2021.
On Behalf of the Board and Employees of
Chairman, President & CEO
About Global Atomic
The Company's Uranium Division includes four deposits with the flagship project being the large, high-grade
Global Atomics' Base Metals Division holds a 49% interest in the
The information in this letter may contain forward-looking information under applicable securities laws. Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Global Atomics' development potential and timetable of its operations, development and exploration assets; Global Atomics' ability to raise additional funds necessary; the future price of uranium; the estimation of mineral reserves and resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and amount of estimated future production, development and exploration; cost of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; currency exchange rates; government regulation of mining operations; and environmental and permitting risks. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "is expected", "estimates", variations of such words and phrases or statements that certain actions, events or results "could", "would", "might", "will be taken", "will begin", "will include", "are expected", "occur" or "be achieved". All information contained in this letter, other than statements of current or historical fact, is forward-looking information. Statements of forward-looking information are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Global Atomic to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Global Atomic and in its public documents filed on SEDAR from time to time.
Forward-looking statements are based on the opinions and estimates of management at the date such statements are made. Although management of Global Atomic has attempted to identify important factors that could cause actual results to be materially different from those forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance upon forward-looking statements. Global Atomic does not undertake to update any forward-looking statements, except in accordance with applicable securities law. Readers should also review the risks and uncertainties sections of Global Atomics' annual and interim MD&As.