He continued, “Following the end of the third quarter, we received the final tranche of funding from Mongolian Mining Corporation (“MMC”) under our
Recent construction photos are included below:
Figure 1: Bayan Khundii Project Site Layout
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6f5309b7-a766-4f7c-ba97-baaeafa4af7e
Figure 2:
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/87a31dd8-9f0d-49b2-a394-9d2a3b9382da
Figure 3:
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/a6700314-0de5-48dc-9d0d-919d7ac8d06d
Q3-2023 Highlights and Significant Subsequent Events:
- Advanced early works, site establishment and procurement for the
BK Gold Project - Early works and site establishment, including installation of temporary facilities, aggregate production, temporary site roads and process plant civils is approximately 80% complete
- Construction preparation is well advanced supporting critical path concrete pours in 2023
- Headcount ramp up achieved in September with approximately 330 employees and contractors on site – no lost time incidents to date
- Remaining detailed design and shop fabrication drawings progressing to schedule, with substantial completion forecast in Q1 2024
- Long lead and critical equipment orders on track with first deliveries scheduled in late Q4 2023
- Contracts for Engineering, Procurement and Construction and Power Provision agreed in principle, with execution planned in the coming weeks
- Delivered Bayan Khundii NI 43-101 Feasibility Study Update (
US$1,800 /oz gold price, unless noted)- Base Case after-tax NPV5% of
US$170 million and 35.3% Internal Rate of Return (“IRR”), increasing toUS$196 million and 38.95% IRR, respectively, at gold price ofUS$1,900 /oz - Life of Mine Earnings Before Interest, Taxes and Depreciation of
US$451 million , increasing toUS$495 million at aUS$1,900 /oz gold price - Total recovered gold of 476,000 ounces, a 25% increase compared to the 2020 FS from an average gold recovery rate of 93%
- All-in sustaining cost (“AISC”) of
US$869 per ounce and upfront capital costs ofUS$88 million , plus a 12% contingency, and$2 million of pre-production costs - Measured and Indicated Resources of 674,700 ounces gold at an average grade of 2.6 g/t gold, and 319,000 ounces silver at an average grade of 1.38 g/t silver
- Proven and Probable Reserves of 513,700 ounces gold at an average grade 4.0 g/t gold, and 220,500 ounces silver at an average grade of 1.7 g/t silver
- Average annual gold production of 86,900 ounces during years 2 through 5 – Life of Mine annual average production of 74,200 ounces gold
- Eight-year project, comprising one-year pre-production, six and three quarter-year operating life and one-year mine closure period
- Adjacent high-grade resources and recent discoveries provide high probability growth options
- Significant benefits to
Mongolia , including Life of Mine royalties and taxes ofUS$143 million and approximately 500 new jobs inBayankhongor Province - Updated NI 43-101 2023 FS filed on
September 25, 2023
- Base Case after-tax NPV5% of
- Delivered on community and stakeholder commitments
- Repaired and upgraded approximately 30 km of off-site roads
- Conducted mine equipment operator training for 60 residents of Bayankhongor province, 75% of 2023 target, the majority of which went on to full-time operator employment
- Completed major community development projects, including potable water supply improvement and public education sanitation facilities
- Remitted 50% of 2023 annual planned donations to local government development programs, in accordance with the statutory Local Cooperation Agreement
Khundii Minerals District Exploration
- Conducted first phase of 2023 gold exploration program at the Greater Dark Horse prospect
- Drilled 1,040 metres intersecting anomalous gold and/or indicator elements in 16 of 18 holes
- Executed IP survey over 9km2 area identifying several targets for follow-up
- Completed ~500 metre trenching program testing near surface, supergene oxide targets similar to those intersected at Dark Horse Mane, returning anomalous mineralization in several areas
Corporate
- Received the final
$30M investment in EM under the terms of theMMC Strategic Alliance - Funds advanced through convertible promissory notes that are planned to be registered as a 50% equity interest in EM by the end of 2023
- Progressed BK Project Finance with international financial institutions
- Due diligence on 2023 FS is the major outstanding item, and is well underway
- Recorded a net loss of
$1,201,100 for the three months endedSeptember 30, 2023 , compared to a net loss of$1,980,438 for the three months endedSeptember 30, 2022 - Exploration and evaluation expenditures, including capitalized expenditures, totaled
$15,373,828 for the three months endedSeptember 30, 2023 , compared to$3,767,892 for the comparative prior year quarter due to primarily due to the commencement of early works for theBayan Khundii Gold Project - Corporate and administrative expenses totaled
$600,595 for the three months endedSeptember 30, 2023 , compared to$870,287 for the three months endedSeptember 30, 2022 , with the year-on-year decrease primarily due to the timing of annual performance bonuses, cost-of-living adjustments and annual performance grants
- Exploration and evaluation expenditures, including capitalized expenditures, totaled
Qualified Person
About Erdene
Forward-Looking Statements
Certain information regarding Erdene contained herein may constitute forward-looking statements within the meaning of applicable securities laws. Forward-looking statements may include estimates, plans, expectations, opinions, forecasts, projections, guidance, or other statements that are not statements of fact. Although Erdene believes that the expectations reflected in such forward-looking statements are reasonable, it can give no assurance that such expectations will prove to have been correct. Erdene cautions that actual performance will be affected by a number of factors, most of which are beyond its control, and that future events and results may vary substantially from what Erdene currently foresees. Factors that could cause actual results to differ materially from those in forward-looking statements include the ability to obtain required third party approvals, market prices, exploitation, and exploration results, continued availability of capital and financing and general economic, market or business conditions. The forward-looking statements are expressly qualified in their entirety by this cautionary statement. The information contained herein is stated as of the current date and is subject to change after that date. The Company does not assume the obligation to revise or update these forward-looking statements, except as may be required under applicable securities laws.
NO REGULATORY AUTHORITY HAS APPROVED OR DISAPPROVED THE CONTENTS OF THIS RELEASE
Erdene Contact Information
Phone: (902) 423-6419
Email: info@erdene.com
Twitter: https://twitter.com/ErdeneRes
Facebook: https://www.facebook.com/ErdeneResource
LinkedIn: https://www.linkedin.com/company/erdene-resource-development-corp-/
Figure 1
Bayan Khundii Project Site Layout
Figure 2
Bayan Khundii Project Process Plant Construction
Figure 3
Bayan Khundii Project Process Plant Construction
2023 GlobeNewswire, Inc., source