Alphamin Resources Corp. announced an update to the development status of its tin project in the DRC. The processing plant front-end crushing circuit has been successfully commissioned on January 8, 2019, on schedule. This includes the primary crusher, two tertiary crushers and the sceening buildings. Ore is now being fed through this circuit to create a stockpile with which the gravity circuit can be commissioned. The process plant in its entirety is planned to be commissioned, on track with the original schedule by the end of March 2019. The underground mine capital footprint was completed at the end of December 2018, two months ahead of schedule. The run-of-mine ore production rate is being ramped up to approximately 1,000 tons per day to achieve the targeted steady-state feed rate to the processing. It is envisaged that the processing plant should ramp up to its nameplate production capacity of tin concentrates from April 2019 to the end of June 2019.