Northland Resources S.A. together with its subsidiaries published an operational update for the Kaunisvaara project, including production figures for the third quarter of 2013. Among other important milestones, the third Vertimill ("VTM") has been installed and is operational. The Company is also expecting to have completed the installment of the ship-loader and the unloading facilities at the Port of Narvik during the fourth quarter of 2013.

The first process line is now complete and operational with the third VTM installed. The second process line is expected to be completed and operational at the end of third quarter 2014. Metso recommenced their work on site in July.

Civil works at Sahavaara stockpile, water purification building and Sahavaara conveyor foundations has recommenced.