VANCOUVER, Jan. 19, 2016 /PRNewswire/ - GREAT PANTHER SILVER LIMITED (TSX: GPR; NYSE MKT: GPL) ("Great Panther"; the "Company") is providing its fourth quarter ("Q4") and annual 2015 production results from its two wholly-owned Mexican silver mining operations: the Guanajuato Mine Complex ("GMC"), which includes the San Ignacio Mine, and the Topia Mine.

2015 Production Highlights (Compared to Full Year 2014)


    --  Record annual metal production:  Metal production of 4,159,121 silver
        equivalent ounces ("Ag eq oz"), a 30% increase
    --  Exceeded 2015 production guidance:  Metal production for the year
        exceeded the annual guidance, which was increased in the third quarter
        to 3.8 to 3.9 million Ag eq oz;
    --  Record annual silver and gold production:  Silver production increased
        25% to 2,386,028 silver ounces ("Ag oz"), while gold production rose 32%
        to 21,740 gold ounces ("Au oz")
    --  Record tonnes milled:  Ore processed increased 12% to 375,332 tonnes

Fourth Quarter 2015 Production Highlights (Compared to Fourth Quarter 2014)


    --  Metal production increased 10% to 1,002,584 Ag eq oz
    --  Silver production was up 1% to 553,189 Ag oz
    --  Gold production rose 17% to 5,637 Au oz
    --  Ore processed increased 2% to 94,874 tonnes

"Continued strong performance in the fourth quarter capped off a transformative year for Great Panther", stated Robert Archer, President & CEO. "We delivered new annual records for silver, gold, and total metal production and beat our already upwardly revised guidance by about 300,000 Ag eq oz. The ongoing ramp up in production at San Ignacio, with higher gold grades, was the major factor in this year-over-year increase. In addition, Topia exceeded one million Ag eq oz for the first time. Operational efficiencies and grade control improved significantly and I would like to congratulate our entire team for a banner year. The increase in production at higher grades allowed us to lower our costs substantially such that Great Panther is well-positioned to withstand this period of depressed metal prices and take advantage of future price rises."




    Consolidated Operations Summary          Q4 2015 Q4 2014  Change   FY 2015    FY 2014     Change
    -------------------------------          ------- -------  ------   -------    -------     ------

    Ore processed (tonnes milled)             94,874   92,574       2%   375,332     335,199         12%

    Silver equivalent ounce production1, 2 1,002,584  911,048      10% 4,159,121   3,187,832         30%

    Silver ounce production                  553,189  550,010       1% 2,386,028   1,906,645         25%

    Gold ounce production                      5,637    4,822      17%    21,740      16,461         32%

    Lead production (tonnes)                     278      285      -2%     1,198       1,154          4%

    Zinc production (tonnes)                     425      406       4%     1,850       1,675         10%
    -----------------------                      ---      ---      ---      -----       -----         ---


    (1)             Silver equivalent ounces for
                    2015 were calculated using a
                    65:1 Ag:Au ratio, and ratios
                    of 1:0.050 and 1:0.056 for the
                    price/ounce of silver to
                    price/pound of lead and zinc.

    (2)             Silver equivalent ounces for
                    2014 were calculated at
                    consistent prices of US$18.50
                    per oz, US$1,110 per oz (60:1
                    ratio), US$0.90 per lb and
                    US$0.85 per lb for silver,
                    gold, lead & zinc,
                    respectively, and applied to
                    the recovered metal content of
                    the concentrates produced.

Guanajuato Mine Complex

Total metal production at the GMC during the fourth quarter of 2015 increased by 11%, to 751,927 Ag eq oz, compared to Q4 2014. When compared to the previous full year, the GMC increased total metal production by 40% to 3,081,258 Ag eq oz, reflecting the ongoing ramp up at San Ignacio. In addition, the continued increase in throughput, coupled with the higher gold grades at San Ignacio, resulted in a 33% increase in gold production for the year to 21,126 Au oz.




    GMC Operations Summary                  Q4 2015 Q4 2014  Change   FY 2015    FY 2014     Change
    ----------------------                  ------- -------  ------   -------    -------     ------

    Ore processed (tonnes milled)            79,651   76,839       4%   309,944     267,812         16%

    Silver equivalent ounce production 1, 2 751,927  677,316      11% 3,081,258   2,193,403         40%

    Silver ounce production                 394,655  396,284       0% 1,708,061   1,239,009         38%

    Gold ounce production                     5,496    4,684      17%    21,126      15,906         33%

    Ag grade (g/t)                              175      178      -2%       192         161         20%

    Au grade (g/t)                             2.39     2.07      16%      2.35        2.03         15%

    Ag recovery (%)                          87.9%   90.1%     -2%     89.2%      89.5%         0%

    Au recovery (%)                          89.7%   91.8%     -2%     90.2%      90.8%        -1%
    --------------                             ----     ----      ---       ----        ----         ---


    (1)             Silver equivalent ounces for
                    2015 were calculated using a
                    65:1 Ag:Au ratio.

    (2)             Silver equivalent ounces for
                    2014 were calculated at
                    consistent prices of US$18.50
                    per oz of silver and US$1,110
                    per oz of gold (60:1 ratio)
                    and applied to the recovered
                    metal content of the
                    concentrates produced.

San Ignacio generated 52% of the overall metal production at the GMC in Q4 2015, and 50% of the total ore processed, compared to 20% and 24% in the fourth quarter of 2014, respectively. The increase at San Ignacio was achieved through expanding production from the wider South Extension zones, which also contributed higher gold grades.

In the fourth quarter 2015, 2,174 metres of surface drilling were completed on the southern extension of the ore zones at San Ignacio with the objective of upgrading the existing mineral resource and guiding continued development.

Topia Mine

Total metal production in the fourth quarter of 2015 at Topia was 250,657 Ag eq oz, reflecting an increase of 7% compared to the fourth quarter of 2014. Similarly, metal production for the full year 2015 was 8% higher, at 1,077,863 Ag eq oz. Both increases were achieved as a result of higher ore grades and slightly higher silver recoveries as well as a strong focus on grade control.




    Topia Operations Summary                Q4 2015 Q4 2014  Change   FY 2015    FY 2014     Change
    ------------------------                ------- -------  ------   -------    -------     ------

    Ore processed (tonnes milled)            15,223   15,735      -3%    65,387      67,387         -3%

    Silver equivalent ounce production 1, 2 250,657  233,732       7% 1,077,863     994,429          8%

    Silver ounce production                 158,534  153,726       3%   677,967     667,635          2%

    Gold ounce production                       140      138       2%       614         555         11%

    Lead production (tonnes)                    278      285      -2%     1,198       1,154          4%

    Zinc production (tonnes)                    425      406       4%     1,850       1,675         10%

    Ag grade (g/t)                              357      338       6%       356         343          4%

    Au grade (g/t)                             0.48     0.45       7%      0.48        0.45          6%

    Ag recovery (%)                          90.6%   89.9%      1%     90.7%      89.9%         1%

    Au recovery (%)                          60.4%   61.4%     -2%     60.6%      56.4%         8%
    --------------                             ----     ----      ---       ----        ----         ---


    (1)             Silver equivalent ounces for
                    2015 were calculated using a
                    65:1 Ag:Au ratio, and ratios
                    of 1:0.050 and 1:0.056 for the
                    price/ounce of silver to
                    price/pound of lead and zinc.

    (2)             Silver equivalent ounces for
                    2014 were calculated at
                    consistent prices of US$18.50
                    per oz, US$1,110 per oz (60:1
                    ratio), US$0.90 per lb and
                    US$0.85 per lb for silver,
                    gold, lead & zinc,
                    respectively, and applied to
                    the recovered metal content of
                    the concentrates produced.

Outlook

Given the significant increase in production in 2015 and the continued low metal price environment, the Company will primarily focus on operational efficiencies and strong grade control in 2016 and build on the successful achievements in these areas in 2015. In addition, the significant growth in 2015 has brought production levels close to plant capacity at the GMC. As such, consolidated production for 2016 is anticipated to be in the range of 4.0 - 4.2 million Ag eq oz (using a 70:1 silver:gold ratio), similar to that in 2015.

On January 14, the Company announced a theft of explosives at the GMC and that an investigation by the authorities had been initiated. Production has not been affected, but should this matter result in a future disruption that could potentially impact the Company's guidance, an appropriate update will be provided at that time.

Although overall production at the GMC is planned to remain at similar levels to 2015, San Ignacio is expected to account for a larger proportion of the throughput. Topia is also expected to produce at similar levels as in 2015.

Consolidated cash costs are anticipated to be in the range of US$5.00 - 7.00 per ounce of payable silver, while All-In Sustaining Costs are projected to be US$13.00 - 15.00 per ounce of payable silver.

Drilling at Guanajuato in 2016 will focus on increasing the resource base at the main Guanajuato mines and at San Ignacio.

The technical information contained in this news release has been reviewed and approved by Robert F. Brown, P. Eng. and Vice President of Exploration for the Company, who is the Qualified Person (QP) for the Guanajuato Mine Complex and the Topia Mine under the meaning of NI 43-101. Aspects relating to mining and metallurgy are overseen by Ali Soltani, Chief Operating Officer for Great Panther.

ABOUT GREAT PANTHER

Great Panther Silver Limited is a primary silver mining and exploration company listed on the Toronto Stock Exchange trading under the symbol GPR, and on the NYSE MKT trading under the symbol GPL. Great Panther's current activities are focused on the mining of precious metals from its two wholly-owned mining operations in Mexico: the Guanajuato Mine Complex, which includes the San Ignacio Mine, and the Topia Mine in Durango. The Company holds an option agreement to acquire a 100% interest in the Coricancha Mine Complex in the central Andes of Peru and holds an option to acquire a 100% interest in the advanced-stage Guadalupe de Los Reyes Project in Sinaloa, Mexico. Active exploration programs are underway at both projects.

Robert Archer
President & CEO

CAUTIONARY STATEMENT ON FORWARD-LOOKING STATEMENTS

This news release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of Canadian securities laws (together, "forward-looking statements"). Such forward-looking statements may include but are not limited to the Company's plans for production at its Guanajuato Mine Complex and Topia Mine in Mexico, exploring its other properties in Mexico and Peru, the overall economic potential of its properties, the availability of adequate financing, and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements expressed or implied by such forward-looking statements to be materially different. Such factors include, among others, risks and uncertainties relating to potential political risks involving the Company's operations in a foreign jurisdiction, uncertainty of production and cost estimates and the potential for unexpected costs and expenses, uncertainty in mineral resource estimation, uncertainty relating to regulatory response to the recent theft of explosives materials from one of the Company's mines, physical risks inherent in mining operations, currency fluctuations, fluctuations in the price of silver, gold and base metals, completion of economic evaluations, changes in project parameters as plans continue to be refined, permitting risks, the inability or failure to obtain adequate financing on a timely basis, and other risks and uncertainties, including those described in the Company's Annual Information Form for the year ended December 31, 2014 and Material Change Reports filed with the Canadian Securities Administrators available at www.sedar.com and reports on Form 40-F and Form 6-K filed with the Securities and Exchange Commission and available at www.sec.gov.

SOURCE Great Panther Silver Limited