COMMENCEMENT OF UNDERGROUND WORKS AT KIDSTON

use

PUMPED STORAGE HYDRO

Genex Power Limited (ASX: GNX) (Genex or the Company) is pleased to provide the following construction update for the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro or the Project).

personal.COMMENCEMENT OF UNDERGROUND WORKS - MAIN ACCESS TUNNEL

During December 2021 and January 2022 (the Period) extensive works relating to the Main Access Tunnel (MAT) for the Project have been undertaken. The commencement of the MAT is ahead of the contract schedule and progressing well.

The MAT makes up a 1.5km long horseshoe profile having dimensions of approximately 6m wide and 6m high. It is graded at 14% (1:7) in a spiral to access the powerhouse cavern which is approximately 250m below ground level. The powerhouse cavern will house the two 125MW Andritz Hydro reversible pump- turbines.

The MAT is constructed using conventional full-face drill and blast excavation methodology, with a single heading taking approximately 6 months to reach the first adit which will provide first access to the powerhouse cavern. Once the first adit is reached, multiple tunnel headings will progress to expedite the powerhouse cavern excavation.

ForWith preparation works for the MAT completed in early 2022 including portal face stabilisation and preparation works, the EPC Contractor joint venture for the Project have formally commenced the underground excavation works with the first major blast for the MAT. Following this milestone, tunnelling operations are now progressing on a 24/7 basis with two shifts per day, which is scheduled to progress the tunnelling works at an average rate of 8m per day over the next 6 months.

T +61 2 9048 8850 E info@genexpower.com.au W www.genexpower.com.au

"It is pleasing to see this iconic project launch successfully and reach this very important early milestone. McConnell Dowell, together with our EPC partner, John Holland are proud to be working with the Genex team to deliver Australia's first privately developed pumped storage hydro project."

CONSTRUCTION UPDATE - ONGOING KEY ACTIVITES

In addition to commencement of the underground works, site activity continues to ramp-up, with works commenced on the following near term construction milestones:

Commencement of procurement and manufacture of key turbine components;

Completion of the blast magazine storage area and access road;

Near completion of the 22kV distribution line with transformer installed with final connection works

onlystill ongoing;

Ongoing aggregate crushing plant and concrete batch plant operations; and

use

Continuation of services reticulation around the site for construction purposes.

UPCOMING KEY CONSTRUCTION MILESTONES

Commencement of full-scale prototype testing of electrical towers for the 186km 275kV transmission line being constructed by Powerlink Queensland; and

22kV electrical connection to Ergon Energy's Kidston substation allowing the removal of temporary electrical connections at the Project site.

The construction program remains on schedule for first generation in Q4 2024.

Commenting on today's announcement, James Harding, CEO of Genex said:

personal

"Following an intense period of site establishment and preparation works, I am delighted that the

EPC Contractor JV of McConnell Dowell and John Holland has formally commenced the

underground excavation works for the Kidston Pumped Storage Hydro Project. This represents a

significant milestone in the project construction timeline which was achieved ahead of schedule.

We look forward to working alongside the EPC JV and keeping the market updated as the program

For

continues to push ahead over the course of this year."

C mmenting on this construction milestone, McConnell Dowell CEO, Scott Cummins, who attended site this week, said:

21 January 2022

02

For personal use only

Figure 1: MAT portal face

Figure 2: McConnell Dowell John Holland Underground Tunnelling Supervisor

explains the process to McConnell Dowell CEO Scott Cummins

21 January 2022

03

For personal use only

21 January 2022

Figure 3: MAT following muck out and descaling operations

Figure 4: Underground Loader mucking out after blasting

04

Figure 5: Schematic of the Main Access Tunnel
down to the Powerhouse Cavern

onlyuse personalThis announcement was approved by the Chief Executive Officer of Genex Power Limited. For

21 January 2022

05

This is an excerpt of the original content. To continue reading it, access the original document here.