Dateline Resources Limited announced the appointment of a mining contractor to the 100% owned Gold Links Project, located in Gunnison County, Colorado USA. The contractor is scheduled to commence mobilizing equipment to site from May 27th, 2021 and will develop approximately 1km (3,000 feet) of underground decline with 4.0mx4.3m (12ft x 13ft) dimensions. The decline will act as a haulage and exploration tunnel, from which the 2150 and West gold veins will be drill tested. The decline will link up with an existing drive at a lower elevation, which will provide a second escapeway for underground personnel and enhance mine ventilation. The decline work is expected to be completed in the fourth quarter of the 2021 calendar year. The underground diamond drill crew is scheduled to mobilise to site in June 2021. The drilling company will undertake 4,000 metres (12,000 feet) of underground drilling from within the decline. The diamond drilling will be located approximately 50-75 metres away from both the 2150 and West veins, which will enable them to complete an anticipated 2-3 drill holes per week. Underground drilling is expected to be completed during the fourth quarter.