Where: Business Route 60 bridge over the BNSF railroad east of Monett

When: Noon, Friday, Jan. 12

What: Business Route 60 bridge over the BNSF railroad is OPEN to traffic after contractor crews completed replacement of the old bridge

Project details:

  • Project replaced old truss bridge with new higher and wider bridge over BNSF railroad east of Monett
  • New bridge no longer has height restrictions because the overhead truss system was removed
  • Demolition of the old bridge began in mid-July
  • Total cost to replace the bridge: $3.7 million
  • Prime contractor: Hartman & Company, Inc., Springfield
  • Contractor has some minor clean-up work remaining on the project that won't impact traffic
  • The original contract completion date was Dec. 29, 2017, but construction delays pushed that date into January 2018

(For more information, call MoDOT in Springfield at 417-895-7600 or visitwww.modot.org/southwest)

(Follow MoDOT's Southwest District:Facebook |Twitter |Instagram|YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

MoDOT - Missouri Department of Transportation published this content on 12 January 2018 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 12 January 2018 19:24:07 UTC.

Original documenthttp://modot.org/southwest/news_and_information/District8Release.shtml?action=displaySSI&newsId=214036

Public permalinkhttp://www.publicnow.com/view/002B796D303A3CC3A98CE980E638405E4EBBD10A